7.4 Installing Analysis Center 3.0 or later

To install Analysis Center 3.0 or later in preparation for restoring the databases on the new computer:

  1. Run the Analysis Center 3.0 or later setup program and install Analysis Center 3.0 or later on the new Data Warehouse computer using the same installation parameters used for the older version of the Data Warehouse computer. You can specify new locations for the Analysis Center components.

  2. After the first successful completion of the OLAP Processing job, disable the job on the Analysis Center 3.0 or later Data Warehouse computer.

  3. (Optional) Back up the Analysis Center 3.0 or later AC_Configuration and AC_Warehouse SQL databases so that you have a copy of these databases at the time of the initial installation.

  4. Connect to SQL Server using an account that has system administrator privileges.